Setup the Hausmate production test equipment as per document 'Testing hardware - equipment setup'.

When testing the Haze it must be plugged into socket 1 of the test Zone Gateway (ZG)

  1. 'Values' below can be checked using the 'Bench, sensors' page of the UI (User Interface - the HostPC's website)
  2. Using at CAT5e or CAT6 patch cable, connect the Unit Under Test (UUT) socket 'ZG1' to the ZG socket '1'.
  3. check all three LEDs on the UUT light the three colours green, blue, red
  4. rotate the encoder clockwise - and check that the HAZE value reduces
  5. rotate the encoder anti-clockwise - and check that the HAZE value increases.
  6. press the encoder and check the PTM value changes from 1 to 0.
  7. On releasing the encoder, the PTM value must change from 0 to 1
  8. If all the above is satisfactory then mark the unit as having passed test buy writing the following - yyyymm-nnn where yyyy is the current year, mm is the current month and nnn is the number of the Haze UUT having passed test this month, (each product type starts at number 0 on the 1st of each month). Use a fine tip permanent marker pen e.g. Staedtler Lumocolour black fine pen Art 318-9 (EAN 40 07817 304563).
  9. Write on the yyyymm-nnn number of the UUT on the outside of the packing bag.
  10. Record on the 'Hausmate production test record sheet' the date, start time, end time, testers name, for each tester's session and the start number (nnn) and end number (nnn) for that session. A new sheet is required for each product, each month.
  11. If any unit fails any test then attach a label stating which part of the test failed e.g. 'LED2, no green', 'PTM, no change' and put the UUT in the fail bin for rework.